Project Profile: Stolthaven Dagenham

Client
Private
Date of completion
September 2016
Value
£7m
Piling and Reinforced Concrete Slabs
Piling and Reinforced Concrete Slabs

Scope of works

 

  • Demolition

  • Site clearance and site infrastructure works (roads, drains, services)

  • Management of contaminated soils and water

Piling and Reinforced Concrete Slabs

Project key points

 

  • Works taking place in a secure and fully operational industrial facility - high risk environment (storage facility for petroleum product)

  • Phased hand over - working closely with client to ensure client direct supply items are fully co-ordinated

  • Piling works consisting of the installation of 1500 DCIS (driven cast in-situ piles) to facilitate new tank bund slabs and walls

  • Construction of reinforced concrete containment bund slabs and walls extending to five metres high

  • Installation of deep drainage from 150mm to 1200mm diameter

  • Installation of multiple large diameter interceptors and pumping stations

  • Construction of reinforced concrete pavement slabs site wide to the fuel terminal