Working closely with our client, Toureen Remediation and Blu-3 UK have collaboratively scrutinised the earthworks design and have provided value engineering options to every element of earthworks undertaken on the project.

Through a detailed CL:AIRE DoWCoP MMP, robust assessment, structural soil stabilisation and soil processing the value has been seen in enabling shallow foundations and a move away from a carbon and cost heavy piled solution and well as providing site won materials in lieu of significant aggregate import driving sustainability whilst improving programme and saving significant cost.

Slough

Client: Blu-3 Ltd

Stats

  • 20,000m3 diverted from landfill
  • 16,000m3 reduced aggregate import